Construction of Concrete Road by length 8 km plus 8 km Gravel at Takhar province, Afghanistan

Description

16.4 km concrete wearing and Gravel Wearing Course road including all other activities. The location of project is at Rustaq distract, Takhar province, Afghanistan it is very complicated area for construction.

Details

Client TDH
Lending Agency Bahir Wafi Construction Company
Project Contact TAK-Road_2019/BWSB/PE
Contract No  
Start Date 01/10/2019
Completion Date 25/12/2019

Pictures

Construction of Foundation for 500 KV Transmission Line and Erection of Towers in Kabul,Afghanistan

Description

500 KV Transmission Line project from Desht-e-Alwan to Arghanda excavation of foundation, Stub sitting, RCC work, curing, backfilling and erection of towers. According drawing of foundation we had different kinds of towers( Class1,Class2,Class3...)

Details

Client DABS
Lending Agency RGM International Company
Project Contact DABS/015/ICB
Contract No  
Start Date 10/10/2017
Completion Date 10/10/2018

Pictures

Gardaz 20 KV Distribution Network Survey and Design at Gardaz city, Paktia province, Afghainstan

Description

Distribution Survey and Design of 18600 consumers at Gardaz and Waze-e-Zadran, the project located at Gradaz city and Waze-e-Zaderan district we had done Topographic survey, Marketing Survey and checking of existing routs.

Details

Client DABS
Lending Agency Angiliuac/State Corps
Project Contact
Contract No DABS/012/ICB
Start Date 01/07/2017
Completion Date 10/3/2018

Pictures

Construction of Foundation for Electrical Towers and Erection of Towers in Helmand Province, Afghanistan

Description

Best Crown Company has done excavation of foundation.RCC work, curing, backfilling and erection of towers. According foundation we had just two kinds of towers(TypeA,TypeB) all foundation were constructed from RCC concrete including piles of towers.

Details

Client USARMY
Lending Agency Assist/ RCC Construction Company
Project Contact +93 (0) 744 2000 73
Contract No  
Start Date 15/07/2016
Completion Date 30/11/2016

Pictures

Construction of Foundation for Electrical Towers in Said-Abad and Wardak Province.

Description

The type of towers were quite distinct from each other for instance,(DA,Type1,DA,Type2,DA, Type3,DB,Type1,2,3 and DC,Type1,2,3) because of that dimensions were also different from each other such as (3.5m*3.5m or 4.2m*4.2m and 5.2m*5.2m) but all foundations were constructed from RCC concrete including piles of towers.

Details

Client USAID/DABS
Lending Agency KEC/ Netracon Technologies
Project Contact +93(0) 789 493 822
Contract No  
Start Date 25/10/2015
Completion Date 10/12/2015

Pictures

Construction of Bankers in Kabul Afghanistan

Description

Construction of RCC Bankers, the diminutions of every Banker (23.25mx8m) and constructed from RCC including walls, floor Slab, Roof slab and foundation. Located in Kabul polycharkhi.

Details

Client USACE ( US Army Corps Engineering )
Lending Agency HKCC (Hashmat Khalil Construction Company)
Project Contact +93 (0) 799552246 or +93 (0) 700209433
Contract No  
Start Date 02/07/2011
Completion Date 01/06/2012

Pictures

Construction of K-Span IDIQ Facilities at MSF Kandak and CAMP HERO Kandahar Afghanistan

Description

Construction of K-Span facilities for 150 person, the diminutions of every Building (60mx20m) Including Latrian area, The K-Span building constructed from RCC foundation and CMU walls, K-Span roof and including all civil work.

Details

Client USACE
Lending Agency EPCL ( Engineering precision Co. Ltd)
Project Contact +93 (0) 797 120 431
Contract No W91B4M-11-D-6506-6002
Start Date 10/01/2012
Completion Date 20/02/2013

Pictures

Construction of Barrack A and Arm Storage in Shorbak (ANA) Base and Halmand province

Description

Description of services, the Barrack dimension (42.75m*10.6m) and army storage(18.6m*18.8m) Foundation of buildings was RCC, CMU wall, rang beam and truss roof.

Details

Client UIP
Lending Agency Barikab Durrani Construction Company
Project Contact +93(0)799 107 283
Contract No  
Start Date 10/03/2010
Completion Date

Pictures

Construction of eight class room School building in Jaghato Distract and Wardak province.

Description

Description of services, Eight class room school dimension (43.2 m *15.25 m) and boundary wall dim (59.6m* 90.4m) the boundary wall Constructed from stone masonry, and School building constructed RCC foundation with column and truss roof. Construction of six toilets and spastic tank.

Details

Client
Lending Agency BSM Afghan Construction Company
Project Contact +93(0)798 102 005
Contract No  
Start Date 30/12/2009
Completion Date 01/07/2010

Pictures

Location survey and drawing from Qargha Canal to Badam bagh pipeline, Kabul province.

Description

Description of services, The canal is a rectangular shaped, stone pointed and is approximately 9, 5 km long and is extended by a 12 inch 2.4KM long pipeline.

Details

Client USAID
Lending Agency Chemonics International Int,ASAP
Project Contact +93(0)799 181 307
Contract No  
Start Date 16/09/2010
Completion Date 31/10/2010

Pictures

Construction of Road Ghazni to Nawur in Ghazni province - Afghanistan.

Description

Description of services…….... Construction of Asphalt road first section from km (0+00 to 6+00) Total length 6km and 10m width thickness of Asphalt 12cm by Tow layer and construction of all structures along the road.

Details

Client USARMY
Lending Agency Omran Holding group Construction Company
Project Contact +93(0) 0202504509
Contract No W5J9JE-10-C-0059
Start Date 01/12/2010
Completion Date 01/11/2011

Pictures

Construction of Road Ghazni to Kolalgo in Ghazni province- Afghanistan

Description

Description of services, Construction of Asphalt road first section from km (0+00 to 5+00). Total length 5km and 11m width thickness of Asphalt 20cm by three layer and construction of all structures along the road.

Details

Client IRD(International Relief and Development)
Lending Agency RWA(Rasuli Wardak Alifi Road and construction Company)
Project Contact
Subcontract No SPR-TO-10-CO9A-2010
Start Date 01/10/2010
Completion Date The Best Crown and BSM Afghan were JV for the mentioned road project

Pictures

Topographic survey and Design of Asphalt road by length 9 km in Midan Shaher area Wardak province.

Description

Description of services, Topographic Survey and design of asphalt road 9km.

Details

Client PRT(Provincial Reconstruction Team )
Lending Agency Unique Builder
Project Contact
Contract No  
Start Date 01/11/2009
Completion Date 30/04/2010

Pictures

Construction of 20 Slab Culverts and 5 Causeway

Description

Description of services, Construction of Slab Precast Culverts and Causeway.

Details

Client AMERIFA
Lending Agency Anwar Mangal Construction Company
Project Contact
Contract No  
Start Date 01/05/2009
Completion Date 30/08/2009

Pictures

Design of Road No.40 in Day Kundi Provinc, Afghanistan

Description

Description of services, Design of Road No.40 from Km(000+000 to 59+000)The DTM of topographic survey provided by IRD.

Details

Client IRD/USAID
Lending Agency NGCC(National General Construction Company)
Project Contact
Contract No  
Start Date 01/05/2009
Completion Date 01/09/2010

Pictures